UK’s flagship AI supercomputer could be delayed until mid-2030s

By Published On: September 25, 2026Last Updated: September 27, 2026
UK’s flagship AI supercomputer could be delayed until mid-2030s

The UK AI supercomputer planned for Loughton will miss its 2027 launch and could be delayed into the mid-2030s because of power supply problems.

The Essex datacentre was announced in 2025 and was expected to begin operating in 2027, but concerns have emerged over whether sufficient electricity will be available in time.

The site is being developed by UK-based startup Nscale, which is seeking a US$35bn (£26bn) flotation this year.

UK Power Networks, which is due to connect the site to the local electricity grid, has reportedly told Nscale that the grid will not be able to supply sufficient power until the early to mid-2030s.

Nscale said it remains “committed to the project” and is examining whether it can generate electricity onsite or accelerate its grid connection.

The planned site, previously occupied by an operational scaffolding yard, has now been cleared.

The government cited the project when announcing its AI strategy in 2025, describing it as the “largest UK sovereign AI datacentre”.

The Loughton site is seeking up to 90MW of electricity capacity, equivalent to the energy consumption of about 315,000 homes.

The delay comes amid wider pressure on electricity infrastructure from datacentre development.

Energy regulator Ofgem said in June that 315 datacentres were waiting to connect to the National Grid, representing 73GW of demand.

That compares with peak electricity demand across the UK of 45GW.

UK Power Networks said it could not comment on an individual project but noted that projects with large energy demands can depend on work across the wider transmission network before they can operate.

A UK Power Networks spokesperson said: “In general, many datacentres, whilst they will connect to our distribution network, are awaiting works on the wider national electricity transmission network before they can begin operation.”

A National Grid spokesperson added: “We’re continuing to work closely with Neso [the government-owned National Energy System Operator], distribution network operators and customers to identify opportunities to accelerate connections where possible and support economic growth.”

A government spokesperson said Neso and Ofgem were working to ensure the right projects received power connections under reforms to the application process.